July looks
to be a very busy month as work gets underway to build the iVinton
fiber network!



Next week,
Patriot Communications based in Cedar Rapids will begin contacting
homes and businesses that have signed up for a site survey. Patriot
team members will start conducting those site surveys the week of
July 15th. As of July 5th, 905 premises in Vinton have signed up to
receive a site survey, so Patriot’s team will have plenty of work
to do once they arrive in Vinton.



Also,
during the week of July 15th construction crews from Central Cable
and their subcontractors will begin preliminary work, with major
construction scheduled to start the week of July 22nd. Construction
will start at the iVinton central office/data center located near the
corner of 3rd Avenue and East 4th Street. Crews will install fiber
from the data center to connect with ImOn Communications’ fiber
ring west of Vinton along two routes.



Soon after
this mainline construction begins, crews will also begin installing
duct from the right-of-way to homes and businesses that have
requested a service line. Unlike the site surveys, this duct
installation does not require you to be home at the time the work is
completed.



July will
also see the unveiling of the iVinton product lineup, including
pricing. The Board of Trustees will be considering the rate schedule
at their meeting on July 23rd.


To sign up to have a survey at your home, click here: www.ivinton.com



Submit a Comment

Please refresh the page to leave Comment.

Still seeing this message? Presh Ctrl + F5 to do a "Hard Refresh".

Comments (0)


To receive each day's headlines to your inbox sign up for our email updates.